TCO C) A project to remodel a bathroom has the following activities. Build this in Excel showing predecessors and paste your answer here (20 points).

ActivityDurationPredecessors

A2 months—

B4 months—

C4 months—

D1 monthA

E5 monthsB

F2 monthsB, C

G1 monthC

H3 monthsE, F, G

I2 monthsD, E

J2 monthsG, H

  1. What are the critical path activities? (10 points)
  2. What is the project’s scheduled completion time? (10 points)