TCO C) A project to remodel a bathroom has the following activities. Build this in Excel showing predecessors and paste your answer here (20 points).
ActivityDurationPredecessors
A2 months—
B4 months—
C4 months—
D1 monthA
E5 monthsB
F2 monthsB, C
G1 monthC
H3 monthsE, F, G
I2 monthsD, E
J2 monthsG, H
- What are the critical path activities? (10 points)
- What is the project’s scheduled completion time? (10 points)