.(TCO A) A project is a temporary endeavor undertaken to create what three things. (Points : 10)

Unique product, service, or objective
Unique project, service, or routine
Unique product, service, or result
Unique routine, service, or result

Question 2.2.(TCO H) The fundamental purpose of the post-project evaluation is to improve future projects. An important component of this evaluation is (Points : 10)

the project audit.
the closure checklist.
lessons learned.
customer satisfaction report.

Question 3.3.(TCO B) The _____ authorizes the project manager to proceed with the project. (Points : 10)

Project Work Order (PWO)
Project Charter
Responsibility Assignment Matrix (RAM)
Project Funding Authorization

Question 4.4.(TCO D) All of the following are strategies for positive risks except _____. (Points : 10)

share
exploit
enhance
transfer

Question 5.5.(TCO F) The primary purpose of a _____ meeting is to identify and resolve problems. (Points : 10)

communications flow
status review
technical design review
problem solving

Question 6.6.(TCO F) Without _____ no one knows what to do. (Points : 10)

status review
communication
technical design review
ideas

Question 7.7.(TCO C) If _____ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing the completion of the project by its required completion time. (Points : 10)

total time
free float
total slack
cumulative slack

Question 8.8.(TCO A) The project plan is executed in the _____. (Points : 10)

initiating phase
planning phase
executing phase
closing phase

Question 9.9.(TCO C) Why are activities drawn in a serial relationship on a network diagram? (Points : 10)

The activities use different resources.
The activities are independent of each other.
From a technical standpoint, the activities must be performed in that sequence.
The order of completion doesn’t matter.

Question 10.10.(TCO F) The _____ is the amount that was budgeted to accomplish the work scheduled to be performed up to that point in time. (Points : 10)

total budgeted cost (TBC)
cumulative actual cost (CAC)
cumulative budgeted cost (CBC)
cumulative earned value (CEV)

Question 11.11.(TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days. (Points : 10)

Day 5
Day 3
Day 1
This cannot be calculated based upon the information given.

Question 12.12.(TCO H) A project audit provides an opportunity to evaluate issues and concerns to determine potential improvements. Some benefits of a project audit are (Points : 10)

reduce project risk, time, and cost overruns.
keep the scope of the project under control.
allow the project team to have good performance.
recommend outsourcing on other projects.