Activity Duration Predecessors Resource Assigned
A. User survey 4 None Gail Wilkins
B. Coding 12 A Tom Hodges
C. Debug 5 A Tom Hodges
D. Design interface 6 B, C Sue Ryan
E. Develop training 5 D Reed Taylor
a. What is the project’s Duration?
b. Using the Resource Usage view, determine which member(s) of the project team has/have been overassigned?
c. Click on the Task Usage view to determine the specific days when there is a conflict in the resource assignment schedule. List the resource and the specific days or range(s) of days there is an overload situation.