0 Comments

Quiz 6

1. Question
: The Control Risks provides outputs to __________ Process
Group(s):

the Closing

the Planning

all

the Initiating

Question 2. Question
: The Control Risk process receives inputs from and provides
outputs to the ___________ process.

Perform Quality Assurance

Monitor and Control Project Work

Validate Scope

Direct and Manage Project Work

Question 3. Question
: Which is not a data input to the Control Risk process?

Direct and Manage Project Work

Perform Integrated Change Control

Develop Project Management Plan

Identify Risks

Question 4. Question
: If the probability of a risk occurring changes, you should
update the:

Influence diagram.

Risk register.

Probability and Impact Matrix.

all of the above.

Question 5. Question
: Risk register updates may include outcomes of the following
except:

risk reviews.

risk assessments.

risk audits.

work performance data.

Question 6. Question
: Which of the following risks should be just monitored?

Low-risk opportunities

Low-risk threats

High-risk threats

High-risk opportunities

Question 7. Question
: The risk score helps the project team:

select responses to risks.

examine the degree to which a risk is
understood.

determine areas most exposed to risks.

develop responses to near-term risks.

Question 8. Question
: The process of evaluating risk process effectiveness is
performed in the ____________ process group.

Initiating

Planning

Executing

Monitoring and Controlling

Question 9. Question
: Quantitative risk analysis:

develops options to reduce threats.

prioritizes risks for further analysis.

defines how to manage risks.

numerically analyzes the effect of identified
risks.

Question 10. Question
: Risk threshold refers to:

the degree of risk that an organization will
withstand.

the degree of uncertainty an entity is willing
to take in anticipation of a reward.

adopting an aggressive resource optimization
technique.

the measures along the levels of uncertainty
at which a stakeholder may have a specific interest.

Order Solution Now