Quiz 3
1. Question
:
Schedule forecasts are an output from which process?
Control Schedule
Monitor and Control Project Work
Develop Schedule
Close Project or Phase
Question 2. Question
: Changes to the schedule baseline can be approved through:
audits.
the Perform Integrated Change Control process.
the Control Schedule process.
the critical path method.
Question 3. Question
: Work performance data output from the Control Schedule
process include the following except:
the deliverables that were over budget.
the deliverables that have finished.
the deliverables that have started.
the deliverables that are in progress.
Question 4. Question
: Earned value management measurement(s) used to control
schedule is/are:
A and C
SV
CPI
ETC
Question 5. Question
: Schedule performance reviews include all of the following
except:
earned value management.
fast tracking.
trend analysis.
critical path method.
Question 6. Question
: Maintaining changes to the schedule baseline is performed by
the __________ process.
Monitor and Control Project Work
Control Schedule
Validate Scope
Perform Integrated Change Control
Question 7. Question
: Crashing for schedule compression works for:
any activity.
only activities on the critical path.
activities ahead of schedule.
activities behind schedule.
Question 8. Question
: Control Schedule is in the __________ Process Group.
Executing
Planning
Closing
Monitoring and Controlling
Question 9. Question
: The difference between float and buffer is:
there are two types of float and one type of
buffer.
buffer is the sum of all the float in the project.
float is calculated for each activity not on
the critical path, whereas buffer is calculated for chains.
the concepts are the same and define the slack
time in the project.
Question 10. Question
: What specifies how formal acceptance of completed
deliverables will be obtained?
Requirements traceability matrix
Control Schedule process
Stakeholder management plan
Scope management plan