Quiz 2

1. Question

Which is a key benefit of the Validate Scope process

Brings objectivity to the acceptance process

Makes changes to the Project Management Plan

Reduces rework

Prepares deliverables for acceptance

Question 2. Question Deliverables that meet acceptance criteria are

verified.

passed by the quality control inspection.

output from the control scope process.

formally signed off and approved by the
customer or sponsor.

Question 3. Question Which is not a data input to the Control Scope process

Direct and Manage Project Work

Perform Integrated Change Control

EnterpriseOrganization

Develop Project Management Plan

Question 4. Question Processes in which of the following Project Management
Process Groups produce change requests

Project life cycle

Planning

Monitoring and Controlling

Closing

Question 5. Question Control Scope process includes all of the following except

monitoring the status of the product scope.

monitoring the status of the project scope.

formulating acceptance of completed project
deliverables.

managing changes to the scope baseline.

Question 6. Question The requirements traceability matrix

is an output of the Validate Scope process.

helps to detect the impact of any change or
deviation from the scope baseline on the project objectives.

is an output of the Control Scope process.

is an output of the Direct and Manage Project
Work process.

Question 7. Question The main difference from the Validate Scope process and the
Control Quality process is

Validate Scope is concerned with acceptance of
deliverables and Quality Control is concerned with ness of deliverables.

Validate Scope verifies deliverables while
Quality Control verifies requirements.

there is no significant difference.

Validate Scope is an input to Quality Control.

Question 8. Question An output of the Validate Scope process is

accepted deliverables.

validated deliverables.

verified deliverables.

rejected deliverables.

Question 9. Question Which is an input to the Validate Scope process

None of the above

Validated changes

Verified deliverables

Accepted deliverables

Question 10. Question Requirements documentation is not an input to the__________
process.

Define Scope

Collect Requirements

Validate Scope

Control Scope