Below is a partial work breakdown structure for a wedding. Create a network diagram for this project, enter Predecessors and answer the below questions:

-What is the duration of the project?

-Which activities are on the critical path?

-Which activities have slack and amount of slack?

WBS Code

Description

Duration(days)

Predecessor(s)

1.

Wedding Project

1.1

Decide Date

3

1.2

Marriage License

1

1.3

Ceremony

1.3.1

Rent Church

5

1.3.2

Florist

4

1.3.3

Create/print programs

10

1.3.4

Hire photographer

2

1.3.5

Wedding Ceremony

15

1.4

Guests

1.4.1

Develop Guest List

12

1.4.2

Order Invitations

3

1.4.3

Address/Mail Invitations

3

1.4.4

Track RSVPs

20

1.5

Reception

1.5.1

Reserve Reception Hall

2

1.5.2

Food and Beverage

4

1.5.2.1

Choose Caterer

3

1.5.2.2

Decide on Menu

5

1.5.2.3

Make Final Order

1

1.5.3

Hire Band

2

1.5.4

Decorate Reception hall

2

1.5.5

Wedding Reception

1

Order Solution Now