Below is a partial work breakdown structure for a wedding. Create a network diagram for this project, enter Predecessors and answer the below questions:
-What is the duration of the project?
-Which activities are on the critical path?
-Which activities have slack and amount of slack?
|
WBS Code |
Description |
Duration(days) |
Predecessor(s) |
|
1. |
Wedding Project |
||
|
1.1 |
Decide Date |
3 |
|
|
1.2 |
Marriage License |
1 |
|
|
1.3 |
Ceremony |
||
|
1.3.1 |
Rent Church |
5 |
|
|
1.3.2 |
Florist |
4 |
|
|
1.3.3 |
Create/print programs |
10 |
|
|
1.3.4 |
Hire photographer |
2 |
|
|
1.3.5 |
Wedding Ceremony |
15 |
|
|
1.4 |
Guests |
||
|
1.4.1 |
Develop Guest List |
12 |
|
|
1.4.2 |
Order Invitations |
3 |
|
|
1.4.3 |
Address/Mail Invitations |
3 |
|
|
1.4.4 |
Track RSVPs |
20 |
|
|
1.5 |
Reception |
||
|
1.5.1 |
Reserve Reception Hall |
2 |
|
|
1.5.2 |
Food and Beverage |
4 |
|
|
1.5.2.1 |
Choose Caterer |
3 |
|
|
1.5.2.2 |
Decide on Menu |
5 |
|
|
1.5.2.3 |
Make Final Order |
1 |
|
|
1.5.3 |
Hire Band |
2 |
|
|
1.5.4 |
Decorate Reception hall |
2 |
|
|
1.5.5 |
Wedding Reception |
1 |