MGT-455 Module 8 Chapter 14 Problem Set

14.8 As the
production planner for Scott Sampson Products, Inc., you have been given a bill
of material for a bracket that is made up of a base, two springs, and four
clamps. The base is assembled from one clamp and two housings. Each clamp has
one handle and one casting. Each housing has two bearings and one shaft. There
is no inventory on hand.

a) Design a product structure noting the quantities for each item and show the
low-level coding.
b) Determine the gross quantities needed of each item if you are to assemble 50
brackets.
c) Compute the net quantities needed if there are 25 of the base and 100 of the
clamp in stock.

14.9 Your boss at Scott Sampson Products, Inc., has just provided you with the
schedule and lead times for the bracket in Problem 14.8. The unit is to be
prepared in week 10. The lead times for the components are bracket (1 week),
base (1 week), spring (1 week), clamp (1 week), housing (2 weeks), handle (1
week), casting (3 weeks), bearing (1 week), and shaft (1 week).

a) Prepare the time-phased product structure for the bracket.
b) In what week do you need to start the castings?