Q. Use the table provided to answer the following questions:

Which activities are on the critical path?

What is the duration of the Project?

Which activity has the most start slack?

*Assume zero as early start (ES) time for activities A, B, C

Activity ID Predecessor Time
A* None 8

B* None 4
C* None 7
D B 5
E A, D 4
F C, D 3
G E 2
H E 3
I F 5
J H, I 2
K G, J 3