Q. Use the table provided to answer the following questions:
Which activities are on the critical path?
What is the duration of the Project?
Which activity has the most start slack?
*Assume zero as early start (ES) time for activities A, B, C
| Activity ID | Predecessor | Time |
| A* | None | 8 |
| B* | None | 4 |
| C* | None | 7 |
| D | B | 5 |
| E | A, D | 4 |
| F | C, D | 3 |
| G | E | 2 |
| H | E | 3 |
| I | F | 5 |
| J | H, I | 2 |
| K | G, J | 3 |