Jack’s Floating Banana Party Company is planning to add a new party vessel for the upcoming season. Jack has identified several activities that must be finished before the start of the season. Use the following information:
a)
Identify the critical path.
Critical path is=
b)
Calculate the expected project length.
Expected project length = ______________________weeks.
| Activity | Activity Time (weeks) |
Immediate Predecessor(s) |
| A | 5 | none |
| B | 5 | none |
| C | 6 | A |
| D | 3 | B |
| E | 5 | C, D |
| F | 10 |
D |