1. Question
: The Monitoring and Controlling Process Group interacts with
__________ Process Group(s):
all
the Initiating
the Planning
the Executing
Question 2. Question
:Change requests may include the following except:
ive action.
preventive action.
key performance indicators.
updates.
Question 3. Question
: Which is not an input to the Integrated Change Control
Process?
Change requests
Change control tools
Organizational Process Assets
Project Management Plan
Question 4. Question
:
A __________ is used to document changes that occur during
the project.
: change baseline
change log
change request
change control board
Question 5. Question
:
For closure documents, the customer acceptance documentation
is an output from the:
:
Control Scope Process.
Control Quality Process.
Validate Scope Process.
Close Project or Phase Process.
Question 6. Question
:
Managing changes to deliverables is performed by the
__________ Process.
:
Validate Scope
Control Scope
Perform Integrated Change Control
Monitor and Control Project Work
Question 7. Question
:
Projects with overlapping phases are:
:
less risky than a project with sequential phases.
more risky than a project with sequential
phases.
neither more nor less risky than a project
with sequential phases.
more risky if a subsequent phase progresses
before accurate information is available from the previous phase.
Question 8. Question
:
Perform Quality Assurance is in the __________ Process
Group:
: Executing
Planning
Closing
Monitoring and Controlling
Question 9. Question
:
Data flows from the Perform Integrated Change Control
Process to:
:
Control Scope.
Control Quality.
All of the above.
Control Cost.
Question 10. Question
:
Data flows from the Close Project or Phase Process to the:
Enterprise/organization.
Validate Scope.
Close Procurements.
Develop Project Management Plan.