8. Choose the scenario where a well thought out Project Organization Chart would add no value as a Project Control Enabler:

A – Involvement by all required groups in an organization leads to a better project plan where nothing is missed

B – If the chart included stakeholders who had no interest in the project (for or against)

C – Project staffing lends itself to organizational resource staffing analysis

D – Project team members can see their roles, which allows the project team to avoid redundant task

9. All of the following create opportunities for a project to go “off track” except:

A- Organizational changes which impact project resources

B – Self Interests of project stakeholders

C – Project team members in-attention to what is being completed

D – Project Manager managing project stakeholders

10. Choose the statement which best describes why Project Methodologies are Project Control Enablers:

A – Creating a unique methodology for each new project promotes diversity in the organization

B – Using a standard project methodology promotes accelerated project startup and allows re-use of previous project plans and schedules

C – Updating project methodologies to correct them for “past sins” gives the new project team an un-fair advantage to be more successful than the previous project teams

D – A methodology is an organizational reminder that it requires too much organizational discipline to bother with.

11. The following project sizes should have project control:

A – Small Projects with a budget of a few thousand dollars

B – Large projects with many external vendors

C – All of these

D – Medium projects which involve only material purchases

12. The real value of a change management plan towards maintaining project control is:

A – It encourages project change

B – It provides a cumbersome process that discourages any form of change

C – It enables an efficient, repeatable change process that gets the project back on track as quick as possible

D – None of the above

13. All of the following are reasons for project teams to be made up of members who perform project roles except:

A – Project roles promote division of labor

B – Project roles funnel the right attention to all project areas

C – Project roles create an opportunity for the organization to train new project managers

D – Project roles concentrate expertise within specific roles

14. While monitoring the project progress, choose the item that the Project Manager is NOT looking for:

A – Deliverable completion

B – Scope Creep

C – Issue Resolution

D – Vendor Invoices for project purchases

15. The best justification for maintaining historical data as a project control enabler is:

A- If a similar project in the past was successful, then repeating past practices will maximize the possibility of current project success

B – It will save time during project startup because you have past project documents

C – It provides an audit trail to show that the past project failure was not the fault of the project team

D – It provides a record of past interactions with vendors

16. Industry best practices suggest that the likelihood of project success increases when which of the following are implemented:

A – Project Control Enablers

B – Deputy Project Managers

C – Approved Project Budgets

D – Weekly status meetings