Question 4: This question has two sections. Section A, and Section B

Section A:

A partially solved PERT problem is detailed in the table below. Times are given in weeks.

Activity

Preceding

Optimistic

Time

Probable

Time

Pessimistic

Time

Expected

Time

Variance

A

—

7

9

14

1.361

B

A

2

2

8

0

C

A

8

12

16

0

D

A

3

5

10

1.361

E

B

4

6

8

0

F

B

6

8

10

0

G

C, F

2

3

4

0

H

D

2

2

8

1.000

I

H

6

8

16

2.778

J

G, I

4

6

14

2.778

K

E, J

2

2

5

0.250

Which activities form the critical path? What is the estimated time of the critical path? What is the probability of completion of the project after week 40?

Section B:

A simple network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are , , . Calculate the critical path and the number of days?