A construction company successfully bid on a contract to repave 20 miles of city road @ $30,000/mile with eight weeks to complete. Two (2) weeks into the project, the company spent $100,000 and completed four miles. Calculate the following terms, making sure that the sign of each term is correct, and indicate whether the company is ahead or behind schedule and budget.

Planned versus snapshot (at two weeks) activities:

BAC

PV or BCWS

EV or BCWP

AC or ACWP

CV

Company is ahead _________or behind ______ budget

SV

Company is ahead _________or behind ______ schedule

CVI

SVI

Project Completion Estimate Activities:

EAC

ETC

VAC